Article by: Hilary Matheson in the Daily Interlake 12/8/2017
The Bigfork High School $14 million addition and renovation was completed ahead of schedule and under budget.
Construction started in May 2016 and was anticipated to be completed by January, but was finished a week before Thanksgiving with approximately $90,000 remaining in a contingency fund.
“It’s pretty remarkable to come in and be ahead of schedule and under budget — and capture what we wanted to accomplish,” said Bigfork Superintendent Matt Jensen.
This achievement took an “extremely good team” said Project Superintendent Mark Casalegno of Hammerquist Casalegno, who himself is a Bigfork High School graduate. In addition to Hammerquist and school district staff, the team included CTA architects.